Dependence on consulting services hired under a separate ongoing ADB-funded project can cause coordination problems and unnecessary delays. For instance, the submission of this project’s 2018 semiannual environment monitoring reports was delayed because of lack of dedicated attention. Better management of the consultants by the project management unit would have helped achieve the intended efficiency.
Project Name
Thimphu Road Improvement Project
Project Number
44240-014