The design and monitoring framework (DMF) requires careful consideration of inputs and a strong results chain to ensure that the project outcome targets are directly addressed by the project outputs and are not likely to be influenced by other factors. Last-mile connectivity solutions, improved signs around stations, and TOD measures could be considered as separate outputs in future metro projects. Gender aspects should be clearly stated in the DMF to highlight ADB’s value addition. Moreover, operational efficiency measured in terms of punctuality of services, reliability of urban transit systems, and affordability may be included in the DMF of future urban transit projects as outcome Indicators.
Project Name
Jaipur Metro Rail Line 1-Phase B Project
Project Number
46417-001
Report Date
Report Source
Self-evaluation
Country
Sector