Overall project success depends to a large extent on the successful implementation of risk mitigation measures carefully identified at appraisal. Weak institutional arrangements and lack of ownership saddled the implementation of this program. A lack of capacity and coordination among different agencies compounded the difficulties. The difficulties could have been minimized or avoided through the timely implementation of risk mitigation measures drawn at appraisal. The measures should be based on a thorough assessment of all potential risks throughout the project period.
Project Name
Urban Public and Environmental Health Sector Development Program
Project Number
39305-013