Sindh Rural Development Project

Projects that are innovative in nature or complicated in design inherently involve delays and require intensive ADB supervision. The potential delays should be factored into the design. Community development projects require additional time and proper arrangements for community mobilization and social preparation processes. ADB experience with such projects, including the Sindh Rural Development Project, shows they generally experience delays of 2 years. The project period should not be less than 7 years.