West Kalimantan Power Grid Strengthening Project

The need for proper arrangements to meet customary ceremony requirements, which can cause delays, should be anticipated in future project designs. For example, because a sacred cemetery to the community was identified at the construction site of a project package, a customary ceremony was needed and conducted to meet the local community's religious requirements.

Project Name

West Kalimantan Power Grid Strengthening Project

Project Number
41074-013
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Preparation
Implementation