Climatic constraints, available working seasons over the year, difficult terrain, availability of experienced local labor, and availability of construction materials need to be adequately considered in deciding the construction completion period. As this was not the case under the project, the Public Works Department was forced to extend the contracts' duration to be able to complete the civil works contracts.