Climatic constraints, available working seasons over the year, difficult terrain, availability of experienced local labor, and availability of construction materials need to be adequately considered in deciding the construction completion period. As this was not the case under the project, the Public Works Department was forced to extend the contracts' duration to be able to complete the civil works contracts.
Report Date
Project Name
North Eastern State Roads Investment Program - Tranche 1
Project Number
37143-023
Report Source
Self-evaluation
Country
India
Applicability
Project Cycle Stage
Implementation