Time allocation or task sequencing

Subscribe to Time allocation or task sequencing

Strengthening Technical and Vocational Education and Training

ADB project teams need to have a realistic understanding of how long it takes host governments to secure internal approvals to avoid delays in completion thatcould impact project performance. Loan effectiveness took place about 5 months after loan signing, some 3 months behind schedule, “due to prolonged government approvals and parliamentary ratification procedures.” This put the project behind schedule almost from the beginning. Subsequent review missions “emphasized the need to accelerate implementation of all planned activities.

North Eastern State Roads Investment Program - Tranche 1

Climatic constraints, available working seasons over the year, difficult terrain, availability of experienced local labor, and availability of construction materials need to be adequately considered in deciding the construction completion period. As this was not the case under the project, the Public Works Department was forced to extend the contracts' duration to be able to complete the civil works contracts.

North Eastern State Roads Investment Program - Tranche 1

As they can lead to time and cost overruns, wide time gaps between the finalization of the estimate, initiation of the bidding process, and awarding of contracts should be avoided. Significant time gaps of 4–5 years between the finalization of the detailed project reports, including cost estimates and the completion of the bidding process were incurred in this project. This led to higher contract costs in comparison to the engineering estimates.

Hai River Estuary Area Pollution Control and Ecosystem Rehabilitation Project

Immediately prior to project approval, a final assessment of the project environment can help identify potential changes or revisions affecting the implementation of subprojects and their components. While scope changes may be unavoidable, the challenge is to proactively identify areas of concern where project circumstances may have already substantially changed prior to implementation affecting coverage of subprojects or components. For example, the higher performance standards brought in after approval for the wastewater treatment plant impacted its financial sustainability.

Second Rural Water Supply and Sanitation Sector Project

Cost overrun can potentially result in a decrease of intended benefits and lower achievement of project outcome. Appropriate estimation of project costs, including contingencies, at appraisal helps in reducing the cost overrun during implementation that could have serious implications on project implementation, given limited funding resources. For instance, a more rigorous consideration of design, including alternative designs and least-cost options, are important to help improve a project’s financial planning and accuracy of cost estimates.