Fiji Ports Development Project (Loan 1902-FIJ)

More thorough stakeholder consultation during project processing could have led to a better project design. The project processing missions could have consulted the key project stakeholders more effectively. For example, a decrease in the port service charge by 50% in 2009 and its elimination by 2010 was cited as a project benefit, but this would have required agreement of the shipping agents and shipping companies to implement. The same applies to the Lautoka reclamation component, which should have been undertaken only after commitments by shipping companies and agents had been obtained. More thorough consultation would have ensured that all parties were aware of their commitments and resulted in better project design.