Based on the actual traffic recorded in 2009 and 2010, the traffic forecast at appraisal was unrealistically high for both the project expressway and parallel G319. The lower traffic and increased project cost have negatively impacted on the project financial reevaluation compared to appraisal. It is, therefore, suggested that a road traffic origin-destination survey be conducted in an appropriate manner, including timing and locations for survey, detailed information on the local and through traffic, accurate information on vehicle categories, and validation of traffic results.
Project Name
Hunan Roads Development II Project
Project Number
35338-013
Report Date
Report Source
Self-evaluation
Country