Supervision of procurement could have been stronger. ADB's project procurement-related review cited potential conflicts of interest, inappropriate prequalification, misleading and incomplete contract documentation, payments not accompanied by adequate documentation, lack of proper evidence and onsite inspection reports accompanying progress payment claims, and poor retention of contract documentation by the school support committees and school construction committees. [Main text, para. 58]
Project Name
Second Education Sector Development Program
Project Number
34388-013
Report Date
Report Source
Self-evaluation
Country
Sector