Electricity Market and Transmission Development Project

The external monitoring group may have to be on board early on the land acquisition and resettlement plan (LARP) implementation. This is to allow sufficient time for the group doing the electricity market to understand the project and the LARP. Due to the highly specialized task of external monitoring group, it is true that not many groups such as those in the academe or non-government organization have actual experience doing the task. The group would need more time to study the issues, and come up with recommendations that can still be incorporated in the on-going process of assisting affected people.