The participation of relevant agencies, effective communication of their role, and broader consultations on possible implementation arrangements at project design ensure effective and efficient inter-agency coordination and project implementation. Under the project, instead of taking full responsibility as the IPIU, UPJN only deployed some staff to the IPIUs and was charging administrative fees for their role including remuneration of their staff that ADB had refused.
Project Name
Dhaka Water Supply Sector
Development Program
Project Number
39405-013
Report Date
Report Source
Validation of self-evaluation
Country
Sector
Themes
Applicability