Attainment of project benefits not within the project scope but instead are dependent on external factors downgrades project performance evaluation. The design and monitoring indicators included household sewerage connections, which were not part of the subprojects’ scope but were provided by the respective urban local bodies (ULBs). This led to dependence on external factors in the accrual of project benefits, thus impacting the final evaluation.
Project Name
North Karnataka Urban Sector Investment Program (Tranche 4 and Multitranche Financing Facility)
Project Number
38254-013
38254-063
Report Date
Report Source
Self-evaluation
Country
Sector
Themes
Applicability
Project Cycle Stage
Preparation
Implementation