Climate risk assessments must be undertaken during project preparation, with results factored into the project design and budgets. The project experienced unforeseen landslides, pointing out the need to (i) improve climate modelling at design stage to incorporate potential climate change impacts on frequency and severity of landslide hazards for projects located in mountainous areas, and (ii) ensure adequate budget or contingency for potential increase of land acquisition during implementation.