Strong political will and commitment at all levels of government authorities have a decisive impact on the effective and efficient implementation of land acquisition and resettlement activities in the context of complex project situation. It is important for an executing agency to be proactive and work closely with local authorities and stakeholders to resolve identified issues on the ground. Monitoring of the implementation of the land acquisition and resettlement plan could start early to identify issues and find effective solutions in a timely manner.