Land acquisition issues in PNG are more difficult to resolve than in other countries, as 97% of land is customarily owned. In this project, In this project, In this project, they were harder to contend with than expected at design stage due to changes in weather patterns that affected travel plans, with many of the sites located at sea. In a project as widely dispersed geographically as this one, more time will also have to be allowed for site access and community engagement activities. Careful consideration of this aspect in implementation timeframes and project scope needs to be undertaken in future similar projects.
Project Name
Maritime and Waterways Safety Project
Project Number
44375-013
Report Date
Report Source
Self-evaluation
Country
Themes
Applicability
Project Cycle Stage
Preparation