Bihar State Highways II Project 

As larger contracts experienced more delays compared to shorter contracts, in future projects, shorter-length contracts may be considered. The termination of contractors was observed to be due to their non-proactive approach while working in discontinuous encumbrance-free stretches of road, poor planning, and inadequate financial capability. Instead of terminating contracts, it would be more desirable to make encumbrance-free land available upfront, release retention money, and create escrow accounts—which were approaches that were successfully implemented.