All of the contractors were local, with inadequate funding, expertise, and equipment, which contributed to implementation delays. With rapid road development in Pakistan, such problems may be worsening. To promote capacity development of local and private contractors, ADB needs to strengthen the capacity-building programs, especially in the area where local construction capacity is lacking.
Project Name
Balochistan Road Development Sector Project
Project Number
34333-013
Report Date
Report Source
Self-evaluation
Country