Integrated Urban Development Sector Project

Under a sector modality, core subprojects should only be included at project appraisal if detailed feasibility studies have shown them to be implementable. Under this grant project, a core subproject (Sopu drainage channel) had to be dropped in the implementation phase when detailed design and feasibility studies revealed huge and unfeasible land acquisition needs.

Project Name

Integrated Urban Development Sector Project

Project Number
38160-032
Report Date
Report Source
Self-evaluation
Country
Report Rating