Foreseeable delays in procurement and disbursements may be overcome by (i) including project readiness measures such as advance actions; and (ii) ensuring dedicated, full-time) and qualified staff with relevant experience for key project management positions. Amounting to 1.5 years in this project, these delays were attributable to the complexity of procedures in Viet Nam, the COVID-19 pandemic, and the large number of project facilities involved.
Project Name
Second Health Care in the Central Highlands Project
Project Number
44265-013
Report Date
Report Source
Self-evaluation
Country
Sector
Themes