Climate Adaptation in Vennar Subbasin in Cauvery Delta Project
In addition to the technical and engineering staff, project management units should include staff with skills in financial management, economics, safeguards, procurement and contracts management, and communication. The project initially encountered difficulties due to the inadequate capacity of the project staff in social and environmental safeguards, contract management, and finance management procedures. An assessment of staff capacity in these areas will identify areas for improvement in future similar projects.