Uplands Irrigation and Water Resources Management Sector Project
Failure to identify and provide the necessary human resources can affect the implementaton of well-prepared projects. This was shown in how the deficit in operation and maintenance specialists and national engineers in the project implementation team and the late recruitment of a gender specialist had caused implementation delays.