Proper assessment of the borrower’s capacity and those of the executing agencies during the preparation phase supports project implementation which will help achieve the desired output and results. A delay in one key project component, due to weak capacity of agencies, could likely cause further delays in the subsequent activities such civil works which hampers the overall project implementation timeline.
Project Name
Second Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program (Tranche 3 and Multitranche Financing Facility)
Project Number
44483-023
44483-024
44483-026
44483-027
Report Date
Report Source
Validation of self-evaluation
Country
Themes
Applicability
Project Cycle Stage
Preparation
