Establishment of professional project administration divisions and retention of experienced and trained government officials in these units can help mitigate the risk of project delays. Project implementation experienced substantial delays despite the preparation of time-bound action plans, project completion was still delayed by 60 months for Lao PDR and 48 months for Viet Nam. The recurrence of this experience in this project may be better addressed by putting in place professional project administration divisions, staffed by trained and experienced personnel.
Project Name
Second Northern Greater Mekong Subregion Transport Network Improvement Project
Project Number
41444-013
Report Date
Report Source
Self-evaluation
Applicability
Project Cycle Stage
Implementation