Uplands Irrigation and Water Resources Management Sector Project

Failure to identify and provide the necessary human resources can affect the implementaton of well-prepared projects. This was shown in how the deficit in operation and maintenance specialists and national engineers in the project implementation team and the late recruitment of a gender specialist had caused implementation delays.

Project Name

Uplands Irrigation and Water Resources Management Sector Project

Project Number
44328-013
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Implementation