Southern Road Connectivity Project

Procurement usually takes extra time due to process-related issues that can be mitigated by (i) strengthening progress monitoring and quality assurance mechanisms during project preparatory work, including bid document Preparation; (ii) appointing dedicated committees and staff, including a technical evaluation committee for road projects, a procurement committee with enforced deadlines, and a staff in the project management unit to coordinate and manage procurement activities; and (iii) providingCapacity development training for the relevant committee.