The significant reduction in the amount of the ADB loan and the program cost with the withdrawal of Goa from tranche 1 and Maharashtra from tranche 2 is reflective of the quality of the work undertaken during the feasibility study stage. Better due diligence and a more rigorous review of the proposals are needed in future multitranche financing facility programs and projects so that similar major changes will not occur at such a late stage in program preparation.
Report Date
Project Name
Sustainable Coastal Protection and Management Investment Program (Multitranche Financing Facility and Tranche 2)
Project Number
40156-013
40156-033
Report Source
Validation of self-evaluation
Country
India
Sector
Themes
Applicability
Project Cycle Stage
Preparation
Topics