Application of lessons from preceding similar projects and regional experience with institutional reforms strengthens the potential for success of projects. In this case, these lessons suggest that (i) strong government ownership is critical to achieving results; (ii) collaboration with development partners is essential to build consensus for reforms; (iii) continued long-term engagement on reforms, supported by investments, is necessary for sustainability; and (iv) monitoring and evaluation are needed for the effective continuation of reforms.
Report Date
Project Name
Power Sector Reform Program (Subprogram 1)
Project Number
54269-001
Report Source
Self-evaluation
Country
Uzbekistan
Applicability
Project Cycle Stage
Preparation
Implementation
Keywords
OP2: Accelerating progress in gender equality
OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
OP6: Strengthening governance and institutional capacity