Khyber Pakhtunkhwa Water Resources Development Project

Extensions in project implementation period provide opportunities not only to fully achieve but also enhance project results. In this case, the agreement on TA extension was premised not only on overcoming delays due to COVID-19 but also to facilitate additional safeguards and technical studies which provided better upstream guidance to the detailed design phase of the ensuing project the TA supported.