Gansu Featured Agriculture and Financial Services System Development Project

Additional ADB support for safeguard implementation should be anticipated for future projects in which the executing and imoplagencies have no prior experience in ESMS. ADB environmental safeguard support was comprehensive for project preparation but less so for project implementation. This was due to a range of factors, which contributed to reduced guidance for the review of subproject safeguard categorization, draft safeguard documents, and support for the implementing agencies. ADB environmental safeguard support for project implementation needs to be strengthened in future projects.

Project Name

Gansu Featured Agriculture and Financial Services System Development Project

Project Number
47046-002
Report Date
Report Source
Self-evaluation
Report Rating