The time provided to establish and operationalize the Super ESCO (energy service company) was not sufficient. The existing policy environment, particularly for government budgeting and accounting, does not support the ESCO concept of an energy performance contract (EPC). The environment needs to be adjusted first to enable implementation of ESCO projects in the public sector.
Project Name
Philippine Energy Efficiency Project
Project Number
42001-013