Initial implementation delays can be reduced by completing more works during project preparation such as (a) preparation of request for proposal for consulting services, (b) approval of feasibility studies by the government, (c) preparation of tender documents for the first contract package; and (d) advance actions for the procurement of consulting services or construction contracts.