Sufficient budget and institutional coordination should be available to minimize the transition period between the completion of resettlement housing and demolition of structures, and relocation of affected persons to their new residences.
Project Name
Fuzhou Environmental Improvement Project
Project Number
35340-013
Report Date
Report Source
Self-evaluation
Country
Sector