Land acquisition in secondary towns can be a lengthy process and can cause significant delays in startup and implementation. Addressing the issue requires strong support from the relevant city corporations and district administrators, motivational campaigns, and adequate compensation packages. Advancing the preparation and approval of the Development Project Proforma to secure necessary funds for land acquisition early in project processing can reduce project startup delays.
Project Name
Secondary Towns Integrated Flood Protection Project (Phase 2)
Project Number
26427-013
Report Date
Report Source
Self-evaluation
Country
Sector