Detailed project preparation and feasibility studies carried out and included in the periodic financing request strengthen project readiness in procurement and safeguards implementation. This could entail conducting comprehensive field investigations and site assessments conducted during the detailed project reporting stage. Monsoon and weather conditions and project readiness for physical works should be considered in drawing up implementation schedules—for both onshore and offshore projects.