Additional approval required by the Ministry of FInance had caused delays to the overall lending process, despite a central monitoring and approval process which was imperative to maintain consistency and objectivity of the project. However, the same level of oversight and central approval process can be implemented in projects where relevant parties are provided with an online tool to manage documentation and other activities.