The project and contract schedule should be realistic, taking into account the technical complexities of the project components, the capacity of executing agencies, consultants and contractors, and the available working season in project towns.
Project Name
Karnataka Urban Development and Coastal Environmental Management Project
Project Number
30303-013
Report Date
Report Source
Self-evaluation
Country
Sector