The recruitment of consultants by executing agencies remains time-consuming. This problem is not specific to the project, but common in all ADB-financed projects in Viet Nam. Delays in consultant recruitment result in delays of the entire associated project. In the future, advance actions and project readiness filters should be applied to minimize start-up delays.
Project Name
Central Region Urban Environmental Improvement Project
Project Number
34355-013
Report Date
Report Source
Self-evaluation
Country
Sector