Fuzhou Environmental Improvement Project

Public announcement of the resettlement cutoff date and its notification to affected villagers should be supported by robust evidence of the established cutoff date such as unambiguous aerial photographs. Local authorities should also try to prevent people from building illegal structures and should rigorously enforce the cutoff date.

Project Name

Fuzhou Environmental Improvement Project

Project Number
35340-013
Report Date
Report Source
Self-evaluation
Report Rating