The Anhui Provincial Government (APG) and ADB should ensure that the executing agency and/or PMO staff has the capacity to carry out the procurement in accordance with ADB guidelines before project procurement starts. This requirement should be made integral to the outputs of the project preparatory TA and recorded in the RRPs.
Project Name
Acid Rain Control and Environmental Improvement Project [Loan 1890-PRC]
Project Number
33441-013
Report Date
Report Source
Validation of self-evaluation
Country
Sector