The project implementation schedule was amended early in the project to comply with the government's request for immediate action and results via the two- pronged approach. Unless there are clear deficiencies in project design, ADB should resist requests to change the design or implementation arrangements early in implementation, because the original project design should be given a chance to succeed. Corrective action can be taken later as problems become apparent.
Project Name
Rural Enterprise Modernization Project
Project Number
38447-013
Report Date
Report Source
Self-evaluation
Country