Project design and implementation schedule. The PCR noted that the targeted timing of some targets in the DMF were unrealistic. Most milestones were front-loaded and planned to be completed within the first 2 years of implementation, hence, the awarding of related contracts and disbursements presented considerable challenges. Since activities to implement the policy reform require intensive coordination among various stakeholders, sufficient time and a degree of flexibility in scheduling need to be provided in the project design (e.g., to respond to changes in government priorities).