Electricity Market and Transmission Development Project

Time needed to deal with rights-of-way. Projects such as this one need to allow sufficient time to assess and address the issues in acquiring right-of-way. The project’s compensation and resettlement problems could have been resolved more quickly if those affected had been made better aware of the property valuation process and the impact the project would have on them. The project could have established a mechanism to deal with disputes, and local government institutions could have been engaged to help resolve them. The project could also have activated its external monitoring group earlier to give it enough time to prepare for assisting those affected.