The need for adequate staff input and maintenance of project records. The project’s midterm review was undertaken 2 years late and almost at the end of the project period at appraisal. This absence of timely oversight and ADB’s poor curating of the project data and documents contributed to the project’s limited success. ADB’s business processes could be improved to retain key project financial and economic analyses records systematically in electronic format.