Loan effectiveness delayed by almost 1 year because of a lengthy government approval process. Executing agency did not commence procurement until the loan was effective although ADB approved advance actions.
Project Name
Northern Power Transmission Expansion Sector Project
Project Number
38196-013
Report Date
Report Source
Self-evaluation
Country