The collection of baseline data should be given high priority. Efforts could have been exerted to ensure that baseline data were established during appraisal stage. Without measurable baseline values set up at appraisal stage, meaningful indicators should be carefully formulated to allow continuous monitoring for updates throughout project implementation. The project’s independent evaluation was hampered by the absence of these baseline indicators.
Project Name
Customs Modernization Project
Project Number
35376-033
Report Date
Report Source
Independent project evaluation
Country