Issues caused by related urban development plans. The implementation of somesubprojects was delayed due to changes in the designs to be consistent with related urban development plans, followed by the contract variations made necessary by these redesigns. It also meant that the affected elements of the subprojects would have to be carried out only when the related urban development plans were to be implemented. Related urban development plans should have been fully considered when subprojects were designed.