Hunan Flood Management Sector Project

Inadequate support for project management. The design allowance for consultant inputs to support project management was inadequate. Adequate loan proceeds should have been earmarked for these services, considering the scale and complexity of the project and the capacities and experience of the provincial project management office (PPMO) and local project management offices (LPMOs).

Project Name

Hunan Flood Management Sector Project

Project Number
37641-013
Report Date
Report Source
Self-evaluation
Report Rating