Delays in recruiting consultants resulted in delays of subsequent activities (detailed design, resettlement planning, environmental management planning, and preparing bidding documents). Despite the start-up delays, the project achieved the targeted outputs, demonstrating that the executing agencies at the provincial level have the capacity for project implementation and the decentralized approach to project preparation and implementation is appropriate.