Some environmental issues surfaced during implementation, which were not considered as risks at appraisal. These include the unanticipated decrease in hydropower output due to continued drought conditions, and the unexpected geological structures and underground water during the construction of the Agdash substation. The drought conditions rendered one impact indicator to be only partly achieved. A more thorough assessment of the environmental risks during the feasibility study stage could have avoided some if not all of these issues.
Project Name
Power Transmission Enhancement Project
Project Number
42085-013